← All postsRunning teams and projects

Material requests against the project budget

When site teams order materials by phone, the store guesses and projects overrun. A quantity budget per project changes that.

The Spiderites team · 23 November 2026

On many projects, materials are ordered by a phone call from site. The store sends what it thinks was asked for, nobody compares it with the plan, and the overrun shows up only when the project closes.

Start from the plan

Give each project a quantity budget: the products it is planned to use and how much of each. From then on, every material request is checked against what the project still has left. A request for more than the plan is visible before it is delivered, not after.

Deliver with a note, verify on arrival

The store delivers with a delivery note, in parts if needed. The requester checks what arrived against the note. Differences are caught on the day, while everyone still remembers the delivery.

Returns are part of the cycle

Surplus material should go back to the store and be recorded. If a request is cancelled, the undelivered quantities return to the project's budget, so the numbers stay true.

One picture for everyone

For every budget line the project shows what was planned, issued, delivered and what remains. In Spiderites that picture builds itself from the requests, delivery notes and returns, without a separate spreadsheet to keep up to date.